102-1 Operating Modes There are three distinct operating modes programmed into each SunWide. Different from SunStar, only one mode of operation being
11 Four Stages of Solar Charging VOLTAGETIMENIGHTNIGHT 4FLOAT 3EQUALIZE 2 PWMABSORPTION 1 BULKCHARGING Solar Charging S
12 Battery Types: The SunWide’s standard battery charging programs are suitable for a wide range of lead-acid battery types. These standard programs
13F. Equalization Interval–Equalizations are typically done once a month. Most of the cycles are 28 days so the equalization will begin on the same d
1410ºC / 50ºF + 0.45 V + 0.90 V + 1.80 V 5ºC / 41ºF + 0.60 V + 1.20 V + 2.40 V 0ºC / 32ºF + 0.75 V + 1.50 V + 3.00 V Temperature Compensatio
15Standard Equalization Programs Both automatic and manual equalizations can be performed using the standard charging programs. Manual Equalization
16The battery manufacturer can recommend the specific gravity or voltage values for your particular battery. Float When a battery becomes fully char
172-3 Adjustability of Load Control When setting in the load control mode, DIP Switch 7 should be placed at OFF. The LVD (low voltage disconnect) a
18The specifications for the diode follow: • a power diode • rated equal or greater than 80 volts • rated equal or greater than 10 amps (SW-10CL) or
192-4 Adjustability of Lighting Control When setting in the lighting control mode, DIP Switch 7 should be placed at ON. After completing the system c
21-1 Introduction The SunWide is an advanced design using a microcontroller for digital accuracy and fully automatic operation. Each model unit can
20 LIGHT TEST Button Press the LIGHT TEST button to enter the testing mode to check if the Lighting Control Switch has been correctly set in order to
212-5 Troubleshooting The SunWide is very rugged and designed for the most extreme operating conditions. Most PV system problems will be caused by co
22troubleshooting the problem. z Check that the load is turned on. Check that no system fuses are defective. Check that no system circuit breakers a
31-3 Specifications MODEL SW-10CL SW-20CL SW-30CL SW-45CLELECTRICAL System voltage ratings 12, 24, 48 Vdc Current ratings-Battery Charge Control 10A
41-4 SW-10CL, SW-20CL, SW-30CL Mounting Dimension Unit: mm L1LSunWideSW-30CLCHARGE LOADBULKEQUALFLOATFAULT FAULTONLVRLVDLIGHT TESTMANUALEQU/LVRBV
51-6 Installation Overview The installation is straight forward but it is important that each step is done correctly and safely. A mistake can lead t
6 Dip Switch 7 ON: Lighting control OFF: Load Control OFF: Lights remain turned off. 2,4,6,8,10: Hours light is turned on after sunset. 2/1,
7Solid Green: Battery discharges to DC load; after six minutes of reconnection process, the green LED will be lit to show battery successfully disch
81-7 Installation Steps: This section provides a brief overview of how to get started using the SunWide controller. However, please review the entire
9connected during the daytime and the array is wired correctly. ※ If the SOLAR is disconnected during installation, the controller will see this as